On 14 September 2025, a gold mine tailings filtration system project in Mongolia reached a major milestone with its first gold pour. During the ceremony, the first gold bars were successfully poured and cast, marking an important step in the mine's transition into production.

This milestone not only represents a significant achievement for the project team but also marks a new chapter in the development of Mongolia's mining industry.

1. Supporting National Strategic Priorities: Gold Production to Strengthen Financial Resilience

As a major gold development project in Mongolia, the mine is expected to contribute to the country's mining sector development and broader economic objectives.

In terms of its resource base, the project has approximately 510,000 ounces of gold reserves, with an average gold grade of 4 g/t. These resource characteristics provide a solid foundation for long-term production.

According to the project plan, the mine is expected to produce approximately 85,000 ounces of gold annually at full production capacity. This output is expected to contribute to Mongolia's overall gold production and become an important source of growth for the country's gold industry.

More importantly, the gold produced by the project is intended to be sold to the Bank of Mongolia at market prices, directly contributing to the country's foreign exchange reserves.

Against a backdrop of increasing global economic uncertainty, gold remains an important reserve asset. Additional gold production could help strengthen Mongolia's financial resilience, support the stability of its foreign exchange reserves and enhance confidence in its position within the international economy.

5.png

2. HOT Provides End-to-End Support from Engineering Design to Commissioning

As a key technology and equipment supplier for the project, HOT undertook responsibilities covering engineering design, equipment supply and on-site commissioning.

The HOT team successfully completed the delivery and commissioning of the tailings filtration system. From filter presses and conveying systems to the automated control platform, the team provided comprehensive technical support to ensure efficient and stable system operation.

During the preliminary commissioning stage, the team also successfully completed integrated system trial runs, verifying the coordinated operation of the entire process and laying a solid foundation for the first gold pour.

The successful first gold pour demonstrates HOT's technical capabilities and project execution expertise in mining equipment integration and engineering services.



3. Win-Win Cooperation: A Milestone Worth Celebrating

The Mongolia gold mine project is not only a major resource development initiative for Mongolia but also an example of regional mining cooperation in the context of the Belt and Road Initiative and BRICS-related cooperation.

Looking ahead, HOT will continue to participate in the mine's ongoing operations and optimisation, supporting the development of Mongolia's mining industry towards greater efficiency, environmental responsibility and sustainability.

The first gold pour represents more than the production of the first gold bars. It also marks an important milestone in HOT's international expansion and stands as a symbol of China-Mongolia cooperation, mutual trust and shared development.